 PROVISION OF INSTALLATION AND COMMISSIONING OF FUEL GAS CONDITIONING UNIT (FGCU) AND ASSOCIATED EQUIPMENT FOR 15MW POWER PLANT FOR GARRAF DEVELOPMENT FACILITY OPERATION 

Iraq Technology for General Contracting was awarded contract to install and commission the Fuel Gas Conditioning System (FGCU) and Associated Equipment thus enable the supply of Conditioned Gas from FGCU System to 150MW Power Plant Fuel Gas Header. The Conditioned Gas would ensure the Bi-Fuel Kit at Diesel Generators and Gas Generators commissioning and operation for supply of electrical power to First Commercial Production (FCP) System including Offsite Facilities and Garraf Base Camp (GBC). 

The FGCU project is brown zone project with scope of work is to install and commission and test operate the FGCU,Construction work include all the Civil, Mechnical and E&I work and then commission and run the unite for continue 72 hours.